High storage capacity reduces refinery turnaround time

 

The Refinery’s Challenge: A tight refinery turnaround deadline required the temporary storage of all wastewater streams.

The Baker Solution: A complete wastewater storage system of 60 tanks and berms, heavy-duty flexible hoses and manifolds was mobilised. This comprehensive Baker system was quickly delivered and installed, allowing the turnaround to stay on its demanding schedule.

Additional customer gains included reduced costs by avoiding external waste disposal and a reduction in the number of vacuum trucks needed. By eliminating shipments of waste the entire process was safer and much faster.

 

Case study - icon - grey - Promo hero image

FEATURED CASE STUDY

REFINERY REPAIR

A refinery needed to repair one of its diethanolamine storage tanks without stopping its production.

Pipes background texture

ARE YOU PLANNING FOR AN UPCOMING TURNAROUND DEADLINE?

Call our helpful team for advice